FERC announces renewed call for science experts

Font Size: A | A | A

FERC announces renewed call for science experts

By: John Seebach  Sunday April 3, 2005
Region: National
Key Words: FERC | ILP | study dispute

Under the Commission's new Integrated Licensing Process, any study dispute will receive a formal hearing by a three-member panel. The panel will consist of:

  • A Commission staff member
  • A representative of the Tribe or resource agency that raised the study dispute
  • A technical expert on the subject

The panel then makes a recommendation as to whether or not the disputed studies are required.

The Commission has initiated a drive to find technical experts in all hydropower-relevant fields that will serve on these study dispute panels. There is no deadline for applications.

If you qualify as an expert in a relevant scientific field, please sign up.