Published on Hydropower Reform Coalition (http://www.hydroreform.org)

Bar Mills : P-2194

Description

The Bar Mills Project consists of a 364-foot-long, 7-foot-high concrete gravity dam that impounds a 263-acre, 5.3-mile-long reservoir. The powerhouse contains two 2.0-MW generating units that discharge water into a 200-foot-long tailrace.

Project power is transmitted through a 30-foot-long, 34/2.4 kilovolt (kV) transmission line connected to the regional grid.


Issues

License requires new construction of upstream passage facility for American eel and other anadromous species.

 

 


Generating Capacity

4

License



License Expiration Date

2048-07-31

License Issued Date

2008-08-26

License Notes

Licensee

FPL ENERGY MAINE HYDRO LLC

Contacts

Default View

Default View

Default View

Certification url

License url

http://elibrary.ferc.gov/idmws/common/opennat.asp?fileID=11787839

Settlement url

http://elibrary.ferc.gov/idmws/common/opennat.asp?fileID=11787839

Source URL:
http://www.hydroreform.org//projects/bar-mills-p-2194