Spearfish

Description

Until 2008, the City of Spearfish had been operating this 4.0 MW project without a FERC license. The project operates in a run-of-river mode.The project is located on the Spearfish Creek in Lawrence County, South Dakota and occupies 57.26 acres of federal lands within the Black Hills National Forest.

Issues

Currently, the project diverts all flows at Maurice dam out of Spearfish Creek and into the project’s underground aqueduct, up to the project’s 120-cfs hydraulic capacity.  This diversion leaves the first several hundred feet of the bypassed reach dry year-round, except when spill occurs at the dam.

The primary issues associated with licensing this project are the costs and benefits of providing minimum flows to the project’s bypassed reach and the effects of minimum flow losses (through aquifer recharge) on downstream aquatic resources and downstream water users, including irrigators. 

Other issues include fish entrainment, fish passage, and the potential for project effects on rare and sensitive species

 

Map

Milestones

DateDescription
5/13/2010Draft Environmental Assessment Released by FERC
9/10/2008License Application Filed