Interior Requests To Reconsider Decision to License Hydrokinetic Project on Mississippi

By: Rupak Thapaliya  Friday January 23, 2009

Through a letter sent last week, the Department of Interior (DOI) has requested FERC for a rehearing of the decision to issue an amended license that allows for operation of hydrokinetic project on the Mississippi river in Hastings, Minnesota.

 


Sullivan Creek Project to require surrendering of application

By: Rupak Thapaliya  Tuesday April 1, 2008

A FERC rehearing on the Sullivan Creek Project concluded that the current license for this project is still valid and the PUD will be required to apply for surrender of license for decommissioning.